Project Goals/Objectives: Collect GIS, landuse, management, and measured data for selected watersheds; Where measured data is available, calibrate SWAT watershed model to measured flow, sediment and nutrients; Simulate nutrient load for current conditions; Simulate for pre- and post- best management plan implementation conditions.
Project Location: Sam Rayburn Reservoir, Segment 0610 and Toledo Bend Reservoir, Segment 0504
Project Costs: Federal ($96,000); Non-Federal Match ($0); Total Project ($96,000)
Project Participant(s): TSSWCB, Natural Resources Conservation Service- Water Resources Assessment Team, and Texas AgriLife Research at Blackland Research and Extension Center
Project Workplan: 04-06
Quality Assurance Project Plan: 04-06
Project Final Report: 04-06