Skip to main content
Skip to Content

Implementing Agricultural Nonpoint Source Components of the Leon Watershed Protection Plan

Project Goals/Objectives: Foster coordinated technical assistance activities in the Leon River watershed; Provide technical assistance to landowners to aid in the development and implementation of Water Quality Management Plans (WQMPs)

For more information please visit: http://leonriver.tamu.edu/our-watershed/

Project Location: The Leon River Watershed below Proctor Lake and above Belton Lake in Comanche, Hamilton, Erath, Coryell, Mills and Bell Counties

Project Costs: Federal ($134,498); Total Project ($134,498)

Project Participant(s): TSSWCB, Hamilton-Coryell SWCD #506, Upper Leon SWCD #525

Project Workplan:  14-03

Project Final Report:  14-03 Final Report

"Protecting and Enhancing Natural Resources since 1939."

Back to top