Overview
Projects to repair and rehabilitate flood control structures across Texas will now be funded due to a $150 million appropriations bill legislators passed this session. The Governor signed the bill into law on June 6, 2019. These structures serve as a critical protection for our state’s infrastructure, private property, and lives. The State appropriated the funds to the Texas State Soil and Water Conservation Board (TSSWCB) to administer through grants to the local sponsors of Flood Control Dams, including Soil and Water Conservation Districts (SWCDs).
Currently there are 2,041 dams which were originally built by the United States Department of Agriculture - Natural Resources Conservation Service (USDA-NRCS) through federal programs in Texas with the understanding that local sponsors would supply operation and maintenance. Local sponsors include Soil and Water Conservation Districts (a subdivision of state government), cities, counties, water control improvement districts, river authorities, and other special purpose districts.
There are 622 dams that are classified as high hazard, meaning there is a potential loss of life if the dam fails; however, only 123 of these meet high hazard criteria. That means that currently 499 dams need rehabilitation and upgrade to meet safety criteria that will adequately protect lives downstream totaling over $1.5 billion, including anticipated federal and local match over a ten-year period.
Project List
In the event that a project on the list below is not prepared to move forward for any reason, it may be moved down in priority and others may be added or upgraded in ranking.
DAM NAME | COUNTY | PROJECT TYPE | STATUS |
ORIGINAL PLAN | |||
Auds Creek 5 | Lamar | Repair | Completed |
Auds Creek 6A | Lamar | Repair | Completed |
Auds Creek Site 7 | Lamar | Repair | Completed |
Big Sandy Creek 26 | Wise | Federal Rehab | Planning |
Big Sandy Creek 43 | Wise | Upgrade | Inadequate Funding |
Big Sandy Creek 44 | Wise | Upgrade | Constr. |
Brady Creek 27 | Concho | Repair | Completed |
Brady Creek 28 | Concho | Repair | Completed |
Brady Creek 34 | Concho | Repair | Completed |
Brady Creek 36 | Concho | Repair | Completed |
Brady Creek 37 | Concho | Repair | Completed |
Brady Creek 38 | Concho | Repair | Completed |
Cedar Creek 126 | Van Zandt | Repair | Cancelled by Sponsor |
Cedar Creek 128 | Van Zandt | Repair | Cancelled by Sponsor |
Cedar Creek 129 | Van Zandt | Repair | Completed |
Cedar Creek 130A | Van Zandt | Repair | Cancelled by Sponsor |
Cedar Creek 131 | Van Zandt | Repair | Cancelled by Sponsor |
Cedar Creek 135B | Van Zandt | Repair | Cancelled by Sponsor |
Cedar Creek 135C | Van Zandt | Repair | Completed |
Cedar Creek 136 | Van Zandt | Repair | Completed |
Cedar Creek 138 | Van Zandt | Repair | Cancelled by Sponsor |
Cedar Creek 87A | Kaufman | Federal Rehab | Constr. |
Cedar Creek 90 | Kaufman | Repair | Completed |
Chambers Creek 1 | Ellis | Upgrade | Constr. |
Chambers Creek 10 | Ellis | Federal Rehab | Constr. |
Chambers Creek 100 | Ellis | Repair | Constr. |
Chambers Creek 107 | Ellis | Repair | Completed |
Chambers Creek 11 | Ellis | Federal Rehab | Constr. |
Chambers Creek 110 | Ellis | Repair | Completed |
Chambers Creek 113 | Ellis | Repair | Constr. |
Chambers Creek 115 | Ellis | Repair | Constr. |
Chambers Creek 125 | Ellis | Repair | Completed |
Chambers Creek 129 | Navarro | Upgrade | Constr. |
Chambers Creek 15 | Ellis | Upgrade | Constr. |
Chambers Creek 23 | Ellis | Repair | Completed |
Chambers Creek 33 | Johnson | Repair | Completed |
Chambers Creek 4 | Ellis | Federal Rehab | Planning |
Chambers Creek 5 | Ellis | Upgrade | Cancelled by Sponsor |
Chambers Creek 6 | Ellis | Repair | Completed |
Chambers Creek 7 | Ellis | Upgrade | Constr. |
Chambers Creek 79A | Ellis | Repair | Completed |
Chambers Creek 9 | Ellis | Upgrade | Constr. |
Chiltipin-San Fernando Crk 2 | Duval | Repair | Constr. |
Clear Fork Trinity River 23 | Parker | Repair | Completed |
Clear Fork Trinity River 33 | Parker | Federal Rehab | Planning |
Comal River 4 | Comal | Federal Rehab | Planning |
Cow Bayou 30 | Falls | Repair | Cancelled by Sponsor |
Denton Creek 21 | Wise | Repair | Completed |
Elm Creek (Centex) 15 | Bell | Repair | Completed |
Elm Creek (Centex) 23 | Bell | Upgrade | Constr. |
Elm Creek (Centex) 26 | Bell | Repair | Completed |
Elm Creek (Centex) 39 | Falls | Upgrade | Constr. |
Kickapoo Creek 2 | Coke | Upgrade | Cancelled by Sponsor |
Lake Creek 2 | Anderson | Repair | Completed |
Lake Creek 3 | Anderson | Repair | Completed |
Lower Brushy Creek 12 | Williamson | Repair | Completed |
Lower Brushy Creek 18 | Williamson | Upgrade | Completed |
Lower Brushy Creek 22 | Williamson | Repair | Completed |
Lower East Fork Laterals 10 | Kaufman | Federal Rehab | Constr. |
Lower East Fork Laterals 3 | Kaufman | Upgrade | Constr. |
Lower East Fork Laterals 9 | Kaufman | Federal Rehab | Design |
Lower Plum Creek 23 | Caldwell | Repair | Completed |
Lower Plum Creek 28 | Caldwell | Federal Rehab | Design |
Lower Running Water Draw 4 | Hale | Federal Rehab | Constr. |
Mountain Creek 11 | Ellis | Repair | Constr. |
Pilot Grove 64A | Hunt | Repair | Federal |
Pine Creek 3 | Lamar | Repair | Completed |
Pine Creek 14 | Lamar | Repair | Cancelled by Sponsor |
Plum Creek 12 | Hays | Federal Rehab | Design |
Plum Creek 14 | Caldwell | Upgrade | Inadequate Funding |
Plum Creek 2 | Hays | Upgrade | Constr. |
Plum Creek 21 | Caldwell | Federal Rehab | Constr. |
Richland Creek 16A | Limestone | Repair | Cancelled by Sponsor |
Salt Creek and Laterals 8A | Wise | Repair | Completed |
San Diego/Rosita Creek 2 | Duval | Repair | Completed |
Upper Cibolo Creek 2 | Kendall | Federal Rehab | Planning |
Upper Cibolo Creek 4 | Kendall | Upgrade | Constr. |
Upper East Fork Laterals 11 | Kaufman | Repair | Completed |
Upper Lake Fork 12 | Hopkins | Repair | Cancelled by Sponsor |
Upper Lake Fork 15A | Hopkins | Repair | Cancelled by Sponsor |
Upper Lake Fork 2 | Hunt | Repair | Completed |
Upper Lake Fork 23 | Hopkins | Repair | Completed |
ADDITIONAL PROJECTS PLANNED | |||
Cow Bayou 10 | Falls | Repair | Completed |
Denton Creek 24 | Wise | Repair | Completed |
Denton Creek 24A | Wise | Repair | Completed |
East Fork Lavon 4 | Collin | Federal Rehab | Completed |
East Fork Lavon 15 | Collin | Upgrade | Inadequate Funding |
East Fork Lavon 16 | Collin | Upgrade | Inadequate Funding |
Elm Creek (Centex) 13R | Bell | Repair | Completed |
Elm Creek (Centex) 14 | Bell | Repair | Completed |
Elm Creek (Centex) 31 | Bell | Repair | Completed |
Elm Creek (Centex) 32 | Milam | Repair | Completed |
Elm Creek (Centex) 37 | Milam | Repair | Completed |
Elm Creek (Centex) 38 | Milam | Repair | Completed |
Elm Creek (Centex) 43 | Milam | Repair | Completed |
Elm Creek (Centex) 4 | Bell | Upgrade | Inadequate Funding |
Lower Brushy 20 | Williamson | Federal Rehab | Completed |
Plum Creek 10 | Hays | Federal Rehab | Constr. |
Upper East Fork Laterals 5B | Rockwall | Upgrade | Inadequate Funding |
Upper East Fork Laterals 5C | Rockwall | Upgrade | Constr. |
Williams 1 | Gillespie | Upgrade | Constr. |